Adjustment of investment project under the judgment and decision of the court and arbitration

a) Implementation order:

- Step 1: The investor submits the documents to the Department of Planning and Investment implementing the investment project.

- Step 2: The Department of Planning and Investment adjusts the Investment registration certificate within 15 days of receipt of a valid document.

b) Implementation method:

- Submit documents: directly at the Division of receiving and returning results (in the head office of the Department of Planning and Investment in Hung Yen province); or through the postal system.

- Receive results: directly at the Division of receiving and returning results (in the head office of the Department of Planning and Investment in Hung Yen province); or through the postal system.

c) Documents:

- A written request for adjustment of investment project (attached with copies of the Decision on investment policy/ Investment registration certificate/ Investment certificate/ Business license/ Investment license).

- Copies of identity card, citizen identity card or passport for individual investors, copies of Business registration certificate or other equivalent document confirming the legal status of investor as institutional investors (For documents of foreign organizations, they must be legalized; documents in foreign language must be translated into Vietnamese, certified by organizations with function of translation).

- Judgment or decision with legal force of court and arbitration.

* Remarks: Individuals/ organizations implementing administrative procedures may submit the copy from the original, certified copy or copy not certified and the original for comparison.

d) Number of documents:

- 01 set (original)

đ) Time limit for settlement:

- Within 15 days of receipt of valid documents

e) Implementing agency:

- Agency directly implementing administrative procedures: Department of Planning and Investment in Hung Yen province;

- Coordinating agency: relevant departments, lines.

g) Subjects implementing administrative procedures:

Investor (individual and organization)

h) Results of administrative procedures:

Investment registration certificate (adjusted) under Form II.2 issued with Circular No. 16/2015/TT-BKHDT.

i) Fees:

None

k) Name of form, declaration:

- A written request for adjustment of investment project under Form I.7 issued with Circular No. 16/2015/TT-BKHDT.

l) Requirements and conditions for procedure implementation:

There is an effective judgment or decision of the court and arbitration.

m) Legal basis of administrative procedures:

- Investment Law No. 67/2014/QH13 dated 26/11/2014;

- Decree No. 118/2015/ND-CP dated 12/11/2015;

- Circular No. 16/2015/TT-BKHDT dated 18/11/2015.

Ý kiến bạn đọc
Gửi ý kiến bình luận của bạn
Họ và tên
(*)
Email
(*)
Nội dung bình luận
(*)
Mã xác nhận
CAPTCHA image
Nhập mã được hiển thị ở hộp dưới đây
 

Ngày 10.10, tại Trụ sở HĐND - UBND tỉnh, UBND tỉnh tổ chức hội nghị l...

Theo Sở Kế hoạch và Đầu tư tỉnh Hưng Yên, qua 9 tháng của năm 2018, t...

Thủ tướng Chính phủ vừa có ý kiến về Đề án bổ sung quy hoạch mở rộng...

Thời gian gần đây, hoạt động thu hút vốn đầu tư trực tiếp nước ngoài ...

6 tháng đầu năm 2018 tỉnh Hưng Yên có thêm 109 dự án mới vào đầu tư, ...

Thăm dò ý kiến
Đánh giá của bạn về cổng thông tin doanh nghiệp tỉnh Hưng Yên?

Đẹp

Bình thường

Xấu

Khác



SỞ KẾ HOẠCH VÀ ĐẦU TƯ TỈNH HƯNG YÊN
Trung tâm Xúc tiến Đầu tư và Hỗ trợ Doanh nghiệp 
Địa chỉ: Số 8, Chùa Chuông, phường Hiến Nam, thành phố Hưng Yên, tỉnh Hưng Yên
Tel: (0221) 3522 668 Fax: (0221) 3525 999
Email: hungyenipc@gmail.com
Chịu trách nhiệm nội dung: Nguyễn Ngọc Khánh – Giám đốc trung tâm
 Số người online: 19      Tổng số lượt truy cập: 6.020.728          Thực hiện bởi: OrientSoft